This article provides a comprehensive guide on how to use the Schedule All feature in BigChange. 

The Schedule All feature of BigChange enables you to Schedule multiple unallocated jobs at the same time, in an optimised way. Scheduling unallocated jobs is the primary use case for this feature, applying defined job constraints, resource availability, intelligent routing to an optimised schedule, without compromising jobs already scheduled.

When using this feature, you can preview the optimised schedule before proceeding, which includes details of the allocated resources, job timings, travel distances and routes. There is also a visual map view of the proposed routes. Finally, jobs that couldn’t be optimised will also be highlighted, including explanatory details.

Does your navigation menu bar look like this? 

imageNewnav.png
Read our Support article about changes we are making, New BigChange Navigation Bar – BigChange

 

How to use the Schedule All feature

To use the Schedule All feature, select “Schedule” from the top menu, followed by “Display” from the side menu. Scroll down and select the “More” icon, followed by “Schedule all jobs”. 

A screenshot of a computer

Description automatically generated

Complete the fields in the “Schedule all jobs” form. 

1. Using Schedule All in BigChange.png

 

     
  Please note, the Contact field is mandatory, and will be used as a start location for resources, should these have not been set in the Admin Settings.   
     

 

blobid2.png

You can also filter the unscheduled jobs by the following: 

  • Specific group of Resources or for 1 resource.
  • Resource skills or vehicle attributes
  • Time period 

You will notice some text on the Schedule all jobs window to alert you to the number of jobs you are about to pass for optimisation. 

Select “Create optimised Schedule”.

You may be presented with an on-screen notification, informing you that some jobs couldn’t be optimised.

A screenshot of a job search

Description automatically generated

The jobs that couldn’t be optimised will be listed, including the reason why. To dismiss this notification, select “Close”.

2. Using Schedule All in BigChange.png

Should you wish, you can view the individual jobs that couldn’t be optimised. To do this, select the link icon for the relevant job.

blobid5.png

Should you wish to proceed, after reviewing the jobs that couldn’t be optimised, select “Create optimised schedule”.

3. Using Schedule All in BigChange.png

You will be presented with a daily preview, listing all the relevant resources, the number of jobs, planned times and distances. A visual of the routes will also be displayed on the map view.

4. Using Schedule All in BigChange.png

By selecting the next arrow, adjacent to the date at the top of the preview, you can view the proposed schedule for other dates set across the original optimisation period.

5. Using Schedule All in BigChange.png

By selecting an individual resource, you will be able to view the full details of their jobs and route. Jobs that were already scheduled, and therefore unable to be optimised, will be highlighted in this view.

6. Using Schedule All in BigChange.png

To view the jobs that a route couldn’t be created for, select “View”.

7. Using Schedule All in BigChange.png

8. Using Schedule All in BigChange.png

 

     
  Please note, if a job is already scheduled, assigned to a resource, including a location and start and end time, it will not be changed by Schedule All optimisation.  
     

 

Should you wish to proceed, after reviewing the optimisation preview, including the resource, jobs and route details, select “Save”. You will then be presented with a pop-up to checking for the final time, you wish to proceed. Select “Yes”.

date.png

The jobs will now be visible on the Schedule. 

Please note, the job activity tab will not update to include a Scheduled Job status line.

 

     
  Please note, the job activity tab will not update to include a Scheduled Job status line.  
     

 

Frequently Asked Questions (FAQs)

How does Schedule All work?

The Schedule All feature analyses all your unallocated jobs and attempts to schedule them against the availability of your resources in the most efficient way, taking into consideration specific constraints set against the individual jobs.

Calculating on a day-by-day basis, it will attempt to create an optimum route for your resources, to fulfil as many jobs as possible. For resources with a fixed start location for example, Schedule All will return the resource to their original start location, within their working hours.

Not all constraints are included within the optimisation process. Current exclusions are “Contact Access hours” and resource “Max. travel distance for a job”. Optimisation also does not currently support multi way point jobs, scheduling from the map view, and routes cannot be edited after optimisation.

 

Will using Schedule All affect Jobs already scheduled?

No. Jobs that are already scheduled will not be changed by the Schedule All feature. Jobs may be added to a newly created route however, all the job details, including the resource, date, start and end time and location will remain unchanged.

 

Do you have any examples or scenarios where Schedule All is best used?

Schedule All is ideal for resources who either start work from either the office, or their home address each day, and do not stay away overnight.

 

Example scenario:

You have just imported a a high volume of PPM jobs with due dates at the end of the month, you can use Schedule All to allocate jobs to your resources based on setting the “to” and “from” dates for the month."